Quality control procedure in finishing section

"Quality control procedure in finishing section "

 ✅✅ Collect Ducuments:
(sample, trims card,measurement spec etc.)

 ✅✅ Thread sucking:
(For removing the loose thread & number sticker garments we use thread shaking machine).

 ✅✅ Size wise bundle:
(Garments come in iron table size wise by the bundle.only one size is allowed in a bundle).

 ✅✅ Inside/outside random audit.

 ✅✅ Collect finish pattern from sample section.

 ✅✅ Pattern Sketch on iron table:(Iron table marking before every style starting).

 ✅✅ Use Iron shoes.

 ✅✅ Iron approval. 

 ✅✅ Excessive WIP:
(Garments not are gathered by more than one style or color in every iron and quality inspection table).

 ✅✅ 100% garments final check:
(Any defective garments will not pass from any operation without alteration and QC pass).

 ✅✅ 100% garments key point measurement:
(100% of garments should a measurement check before packing. Measurement defects garments should not advance for packing. Defect means out of tolerance, if it can rectify, it will be pack otherwise it will be count as a reject.)

 ✅✅ 100% garments get up check:
(Q.I check there is something odd looking at a glance in whole garments, like out of shape, spot, poor pressing etc.)

 ✅✅ Hourly /Lot audit.
(Finishing Quality auditors audit GMTS before moving GMTS to packing area from every bundle using AQL 1.5. If the audit pass, GMTS will move forward for packing. If Audit fails, an auditor will give back GMTS to the Quality checkpoint area to recheck. After completing recheck, finishing Auditor will re-audit.)

 ✅✅ Mock up preparation:
(Specific written instruction for every operation with garments form mockup as visual instruction for attaching the sticker, measurement, quality inspection, folding, and packing).

 ✅✅ SKU/UPC/PO check with care label.

 ✅✅ 100% garments metal detection pass:
(100 % of garments metal detection is to follow to ensure garments free from a needle, sharp tools, and any types of metal as ensured product quality.)

 ✅✅ 9/24 points calibration metal detection machine every hour.

 ✅✅ Folding approval. 

 ✅✅ Finishing inline inspection. 

 ✅✅Assort & shade check:
(Ratio & Shade Checking before seal, the carton Q.C check the ratio & garments shade that, the ratio & garments shade is as per buyer requirement & same shade in one carton. If both think is okay Q.C gives a sign inside of the carton, then the carton should seal in front of Q.C.)

 ✅✅ Pre final inspection:
(There is an in-house pre-final audit for self confirmation, done by the  GPQ.  He audits by 2.5 AQL as receiving the GPQ pass report we offer for a final inspection. Our A.Q.L chart is shown as bellow link.

 ✅✅ Final inspection:
 ☑️☑️N:B: After receiving from wash we start finishing the procedure, at the same time we press covering all sizes & colors to see the measurement, wash standard, hand fill & any wash defect by wash factory. Also, carton & poly, measurement ensure by the first production.

 🔷🔷 Finishing is the last step of the garments industry. Quality Control is necessary for every stage of garments production for the purpose of making a quality product, finishing the garments, prepare for shipment, and finally deliver to the garments buyer. So, finishing is a very important process in garments. To ensure finishing quality control by the garments manufacturer a finishing quality control SOP of the garments Industry is to prepared and followed accordingly.

❤️❤️ If you need more guidelines regarding this then please do not hesitate to ask, our comment section is always open for your opinion.